prim73702:Earned Value is not spreading correctly when using the Future Bucket curve.
| Solution ID: prim73702 |
| Earned Value is not spreading correctly when using the Future Bucket curve. |
| Status: Reviewed |
| Version(s): 6.1, 6.2 |
| Problem: | Earned Value is not spreading correctly when using the Future Bucket curve. |
| Fix: | Earned Value will not spread against the curve assigned, however, the total Earned Value Cost/Units will be calculated using the manual curve. For example, Below are two activities:
In the Resource Usage Spreadsheet, the bottom view has the same two activities but notice the ’Linear’ activity has a Linear Curve. ‘Manual’ Activity has a Manual Curve. Both have $80.00 budgeted and are 50% complete. Notice the ‘Manual’ activity has $25.00 of Earned Value Cost while Linear has $40 of Earned Value Cost. This is because activity ‘Manual’ has a total of 25 units each worth $1 which equals $25. Also, since the total is 25 units they are spread linearly across the week. |

complex post. due one decimal where I bicker with it. I am emailing you in detail.