Solution ID: prim80259
How to export Impacted Risk Data to Microsoft Project.
Status: Reviewed
Version(s): 8.0, 8.1, 8.2, 8.5, 8.6

Problem: How to export Impacted Risk Data to Microsoft Project.
Problem: Is it possible to send Risk Register data to MSP.
Problem: How to send an impacted risk plan to Microsoft Project.
Fix: Impacted risk plans, like all plans, can be exported to Microsoft Project by going to:

File | Microsoft Project | Export to .mpp


Unfortunately, Risk Register data can not be viewed in MSP.  However, it can be exported to Excel.  From the Risk Register, go to:


 File | Export Risk Register as


Give the file a name and choose to save it with a .xls extension.