prim80554:How to display curtain downtime in Pertmaster.
| Solution ID: prim80554 |
| How to display curtain downtime in Pertmaster. |
| Status: Reviewed |
| Version(s): 8.0, 8.1, 8.2, 8.5, 8.6 |
| Problem: | How to display curtain downtime in Pertmaster. |
| Problem: | What is Curtain Downtime? |
| Problem: | Is it possible to display non-working time from a calendar across all tasks in the Gantt Chart? |
| Fix: | Curtain downtime can be used to display downtime based on a selected calendar. The downtime will be shown for all tasks in the Gantt Chart, even for those to which it does not apply. It has no effect on the scheduling of tasks but is useful for highlighting periods in a project such as winter, hurricane season or canals frozen. To show curtain downtime: Launch Pertmaster
|